Client: Cameco, Key Lake Mine

Duration of the Work: 281 days

Area of Work: Electrical & Instrumentation

Comments: Installed 15 kV Power Cabling including terminations and connections. Installed 600 V Control Cabling and terminations. Installed MCC’s, Stand Alone VFD’s, Dry-type Transformers, Distribution Panels, 15 kVA redundant UPS system, disconnect switches, and welding receptacles. Installed numerous fluorescent and emergency lighting fixtures, heat trace, and sump pumps. Installed Cable Tray complete with fireproofing and grounding. Installed Grounding Rods complete with cable terminations and connections.